Case studies

Three structural decisions

The moments on a job site where a decision made the difference between what the plans showed and what the house needed to actually hold.

Rebar cage running along the formed edge of an elevated concrete floor, storm clouds over the canal

Bridge-Grade Steel, Built for a Family Who Refused to Evacuate Again

Bridge-grade steel most residential builders have never touched — engineered for a family who lost their last home to a prior hurricane and wanted the next one built to survive whatever comes.

See the full story →
Close-up of a large built-up beam along a CMU wall, fitted with roughly two dozen blue joist hangers, shored from below on steel posts

The Beam That Would Have Failed

A wall came out during design and left a beam unable to carry the load above it — caught before the pour, then a call back six months later for a problem nobody saw coming.

See the full story →
Overhead view of a steel rebar cage set into an excavated footing trench, with intersecting reinforcement grids and string lines marking the layout above

The Soil Test That Redesigned the Foundation

A soil boring test nobody required found the ground too soft for the original plan — the foundation redesign that followed, and the two-month supply problem it created along the way.

See the full story →