Your Pre-Drywall Walkthrough: What You Can Still Change

Posted November 4, 2026. The Nikic practices described here are as of November 4, 2026.

Once construction starts, the last cheap moment to change a custom home is when it’s framed and nothing else is in the walls. The rooms stand at full size for the first time, and moving a wall or a doorway is still a change to the frame. Nikic holds its walkthrough at exactly that point: after framing, before the electrical, plumbing and HVAC rough-in. This is the buyer’s side of that walk: what to look at, what to bring, and what a change costs.

What the walkthrough is

You walk the framed house with Sasa, room by room, and say what you’d move. It’s built into every Nikic project, and it’s the first time you can stand in the rooms rather than read them off a drawing. How the walk fits into the rest of the build is on our process page. This post is about what to do while you’re there.

Why it happens before the wiring and plumbing go in

After rough-in, a moved wall is no longer just a framing change. The electricians, plumbers and HVAC installers who ran wire, pipe and duct through it have to come back and redo what they installed. Before rough-in, there’s nothing in the wall to redo.

If you’ve been reading about pre-drywall walkthroughs, you may expect to check where the outlets, switches and vents ended up. At this walk they aren’t in yet. You’re not checking their locations. You’re deciding them.

What to look at, room by room

Drawings are good at dimensions and poor at volume. Standing in the framed rooms fixes that. In each room, look at:

  • The layout against the plan. Each wall where you expected it, and each room opening into the next the way you pictured.
  • Proportions and ceiling heights. How the room feels at full size, not how it measured on paper.
  • Door and window openings. Where each window sits in its wall, and what you’ll see through it.
  • Sightlines. What you see from the front door, from the kitchen, from where the bed will go.
  • Stairs and closets. Their size and position, now that you can stand next to them.
  • Niches and soffits. Any framed recesses or dropped ceilings, and whether they’re where you want them.
  • Where things will go. The bed, the sofa, the TV, a pendant over the island. Those decide where outlets, switches, lights and plumbing belong, and right now those locations can still be set to suit.

This is a walk for how the house will live, not a structural inspection. The structure is inspected separately, later in the build.

What to bring

  • Your selections and notes. Furniture sizes, appliance choices, anything that needs a particular wall, outlet or clearance.
  • A phone. Photograph every wall before it closes. Those photos show what’s behind the drywall long after it goes up.

What a change costs at this stage

In practice, small adjustments cost materials only. Larger changes usually carry both a labor fee and a change-order fee. A change that means revising the permit is priced as a change order, and you’re told what it does to the schedule.

So a larger change isn’t free here. It’s still cheaper now than after the walls close, when the same change means trades coming back and finished surfaces coming out. How Nikic’s fees are structured is on our pricing page.

Why the framing inspection comes after rough-in

Two events in the sequence are easy to confuse. Your walkthrough with Sasa comes before rough-in. The framing inspection comes after it.

That order is deliberate. Nikic moved the framing inspection to after the electrical, plumbing and HVAC rough-in once those contractors were found cutting joists during installation. Inspecting the frame after the trades have been through it means the framing that passes inspection is the framing that gets closed up.

What a change costs once the house is finished

A Belleair Beach spec home Nikic built shows the other end of the scale. Its plans left out an elevator. Once the house was finished and listed, buyer feedback pointed to the missing elevator. Nikic came back and retrofitted one into the completed house: cutting into the slab, pouring new footings, cutting through structural floor trusses while the building above was temporarily supported, and building a new shaft from the foundation up through the roofline, all while preserving the finished interior.

No buyer existed when that house was framed, so there was no walk at which to ask for an elevator. The comparison is in the work. At the walkthrough, a change is made to a frame with nothing in its walls. After the house was finished, it meant cutting through slab, floor trusses and roofline around finishes that had to stay intact. The Belleair Beach case study has the full story.

Before your walk

If you’re building with Nikic, the walkthrough is already part of your build, and Sasa will be there. If you’re still comparing builders, ask each one two questions: when will I walk the framed house, and what does a change cost at that point? If you’d like to talk through your own project, start a conversation.